The suggested time specific activities table and timeline chart are prepared based on the activities to be undertaken in the selected micro-watersheds. DPR preparation for 75 micro-watersheds will be prepared in 1st two years using the developed DSS and field verification and in case of delay in the development of the new model/DSS the DPR will be prepared with the use of the existing methods/models. Subsequently, refinement of the DSS and its application for hydrological assessment in remaining 332 micro-watersheds will be taken up during 3rd, 4th and 5th year of the project.
1 | 2021-22 | • Selection of watershed
• Procurement of field and lab equipment, hardware, software • Engagement of contractual manpower • Complete field instrumentations in 2 model MWS for model calibration and validation and need based instrumentation in 12 MWS • Secondary data collection, data analysis • Thematic maps preparation • Training for knowledge upgradation of scientists/ project staff through HRD • Data monitoring, analysis and reporting • Review meetings/workshops etc. |
2 | 2022-23 | • Set up of hydrological model, groundwater model and crop model, simulation, calibration and validation for selected MWS
• Development of protocol and programming for DSS • Preparation of DPR for MWS that includes model MWS, monitoring MWS and LRI MWS • Capacity building of scientists/ staff in RS/ GIS/ Hydrological modelling • Data monitoring, analysis and reporting • Review meetings/workshops etc. |
3 | 2023-24 | • Preliminary data collection for the un-treated micro-watersheds of the selected districts
• Thematic maps preparation • Refinement of DSS • Surface water, groundwater and crop model simulation • Scenario generation in DSS and recommendation for positioning of SWC structures, groundwater well and recharge structures, crop selection and crop management in MWS • Technical support in Preparation of DPR for MWS • Data monitoring, analysis and reporting • Review meetings/workshops etc. |
4 | 2024-25 | • Thematic maps preparation
• Surface water, groundwater and crop model simulation • Scenario generation in DSS and recommendation for positioning of SWC structures, groundwater well and recharge structures, crop selection and crop management MWS • Technical support in Preparation of DPR for MWS • Scenario generation in DSS and recommendation for positioning of SWC structures, groundwater well and recharge structures, crop selection and crop management in MWS • Technical support in Preparation of DPR for MWS • Data monitoring, analysis and reporting • Review meetings/workshops etc. |
5 | 2025-26 | • Preliminary data collection for the un-treated MWS of the selected districts
• Thematic maps preparation • Surface water, groundwater and crop model simulation • Scenario generation in DSS and recommendation for positioning of SWC structures, groundwater well and recharge structures, crop selection and crop management in MWS • Capacity building of stakeholders • Technical support in Preparation of DPR for MWS • Data monitoring, analysis and reporting • Review meetings/workshops etc. • Implementation of watershed activities by PIA |